Companies·2 min read·The Block

Anthropic Leases 191 MW From a Bitcoin Miner for $9.1B

Riot Platforms signed a 20-year, 191-megawatt data-center lease worth $9.1 billion at its Rockdale, Texas campus. Riot did not name the tenant; Bloomberg reported it is Anthropic.

ANTHROPIC · COMPUTE Claude's new landlord mines bitcoin 191 MW by June 2028 $9.1B base, 20-year term 96 MW first power, Dec 2027 ROCKDALE, TEXAS Riot Platforms · 20-year lease to June 2048 · tenant reported by Bloomberg, unconfirmed BITSMINDS.COM
Share:

Bitcoin miner Riot Platforms has signed a $9.1 billion agreement to lease 191 megawatts of IT capacity to a frontier AI lab. Riot did not name the counterparty in its announcement; Bloomberg subsequently reported, citing people familiar with the transaction, that the tenant is Anthropic.

The capacity sits at Riot's Rockdale campus in Texas and arrives in phases: 96 megawatts by December 2027, with the full 191 megawatts due by June 2028. The lease runs 20 years, through June 2048, and carries two five-year extension options that would lift the total contract value to $16.1 billion if both are exercised. Riot has secured a $573 million interim financing facility from Morgan Stanley to cover development costs.

For Riot the deal is a pivot, not a sideline. The company reported second-quarter revenue of $174.2 million against a net loss of $237.2 million — the familiar squeeze on bitcoin miners whose power contracts and shells are worth more to AI labs than to hashing. CEO Jason Les said Riot has now executed leases totalling 241 megawatts in just over six months, representing roughly $9.8 billion of long-term contracted revenue with what he called two of the most important companies in the AI ecosystem. Riot shares closed down 5.46% on Monday, then jumped 25.26% in after-hours trading to $24.30.

On Anthropic's side the lease is one more line in an aggressive compute build-out that increasingly runs outside the traditional hyperscalers. The company has already committed to SpaceX's Colossus data center and sits at the center of Google's TPU financing structure. Signing a two-decade lease with a bitcoin miner extends the same logic: the binding constraint is energized megawatts on a schedule, and whoever already holds the interconnect gets the contract.

The timelines are worth noting against the size of the number. Nothing here is capacity Anthropic can use this year — first power lands in late 2027, and the headline $9.1 billion is base revenue spread across two decades. What the deal actually buys is a claim on Texas grid capacity that will not exist for another 18 months, priced today because by 2028 it will not be available at any price.

Riot has not confirmed the tenant on the record, and Anthropic has not commented publicly. Until one of them does, the identification rests on Bloomberg's sourcing rather than a filing.

Want AI news before everyone else?

The morning's most important AI stories, straight to your inbox. No fluff.

Related Articles

INTEL · PROPOSED COMMON STOCK OFFERING $15,000,000,000 plus a 30-day underwriters’ option for $2.25B more Physical AI robotics and edge silicon Purpose-built silicon custom AI accelerators Packaging, wafers advanced packaging, foundry 2026 capex guidance raised to about $20B — and rising again in 2027 BITSMINDS.COM
Companies

Intel Seeks $15B in Stock to Fund Its AI Buildout

AMD · TAALAS ACQUISITION · AUGUST 6, 2026 The weights move into the silicon TODAY: GPU PLUS MEMORY WEIGHTS COMPUTE Every token waits on the memory bus. TAALAS HC1: ETCHED IN No memory bus. Also no second model. TSMC 6nm · 815 mm² · 53 billion transistors · Llama 3.1 8B BITSMINDS.COM
Companies

AMD Buys Taalas to Etch AI Models Into Silicon

DISCOVERY LOOP · AUGUST 5, 2026 Four names leave Google to close the loop ×1000 IN PARALLEL PROPOSE RUN EVALUATE ITERATE Jeff Dean Sanjay Ghemawat Quoc Le Oriol Vinyals DEAN AT GOOGLE 27 yrs STRUCTURE Public benefit BITSMINDS.COM
Companies

Jeff Dean Leaves Google to Automate Science Itself